Subject: Re: Questions for Becky
One concerning aspect of PacifiCorp's handling of the fire liability is that they allegedly reneged on their agreement to provide sufficient power to four Amazon data centers. Amazon claims PacifiCorp is supplying the first data center with “significantly less power than promised.” They also said it has provided no power to the second data center, and has refused to complete its own standard contracting process for the third and fourth centers.

https://finance.yahoo.com/news...

PacifiCorp's reputation with residential customers is already toast. Now they're ruining their reputation with data center customers. PacifiCorp must be very careful that they are willing to do that.